After the severe setback occasioned by the decision to undertake the North African operation, planning for the invasion of northern France was revived in the spring of 1943. The approval of COSSAC's OVERLORD plan at QUADRANT in August, and subsequent decisions at the SEXTANT Conference, gave new impetus to preparations for the cross-Channel operation. In the latter half of 1943 the major Allied and U.S. tactical commands and subcommands of the forces to be engaged in continental operations were set up in the United Kingdom, and in January 1944 COSSAC became Supreme Headquarters, Allied Expeditionary Force (SHAEF). Chapter VI
The Invasion of NormandyDuring the next five months the projected OVERLORD operation underwent continued study, and detailed plans for its implementation were worked out. As finally developed, OVERLORD called for airborne landings in the Caen and Carentan areas, closely followed by amphibious assaults on the Normandy beaches on the east side of the Cotentin peninsula and between the Orne River and the Carentan estuary. The assault was to be followed by the early capture of Cherbourg in the west and a rapid advance inland. The beachhead would be simultaneously expanded southward and eastward to include the Brittany peninsula and the area between the Loire and Seine Rivers. This lodgment area, which would serve as the springboard for further offensive operations, was to be secured in a three-month period.1
The mounting of OVERLORD was begun in mid-May 1944, and on 6 June the assault on the Continent got underway. The transportation task involved in the execution of the operational plan was formidable. A force of 1,350,000 US troops, together with their organizational equipment and vehicles, had to be moved from the United Kingdom to the Continent in a ninety-day period. The support of this force required the shipment from Britain and directly from the United States of vast amounts of ammunition, rations, clothing, fuel and lubricants, construction materials, rolling stock, and other materials. On the far shore, men and cargo had to be received over beaches and through badly damaged ports. Motor transport operations had to be established to handle beach and port clearance and all other interior transport pending the capture and rehabilitation of railways. Obviously, such operations required months of intensive planning and preparation. In the period before D Day, the Transportation Corps in the United Kingdom played an important part in laying the groundwork for outloading and supporting US forces engaged in OVERLORD, and for developing transportation operations on the Continent.
Transportation Corps planning for continental operations began early, but was limited by the lack of firm tactical plans. Until the fall of 1943 Transportation planning was handled for General Ross by a small section under Colonel Traub. Traub participated in various conferences held by COSSAC, worked with the British on plans for a joint stockpile of transportation matériel, and pushed through troop lists and operational projects prepared by various divisions in the Transportation Corps' theater headquarters. In the absence of definite operational plans, determination of matériel requirements was made on the basis of the theater's projected troop strength.2 The Establishment of Planning Machinery for Continental Operations
Once the OVERLORD plan was given limited distribution, and various Allied and US headquarters had come into being, the theater chief of transportation was able to begin detailed planning. On 14 September 1943 he activated an advance echelon to plan for transportation operations on the Continent. Headed by Colonel Traub, who was designated a deputy chief of transportation, the Advance Echelon was set up to parallel the parent organization. By the spring of 1944 it had seven divisions-Military Railways, Marine Operations, Movements, Motor Transportation, Administration, Intelligence, and Supply.
As the Army's logistical agency, SOS was not only responsible for mounting and supporting US forces engaged in OVERLORD but was also charged with developing the communications zone on the Continent. At the direction of SHAEF, SOS activated the Forward Echelon, Communications Zone (FECZ), in February 1944, to draw up plans for logistical operations on the Continent during the entire ninety-day period, and to precede it to the Continent and prepare the way for a Communications Zone headquarters. The Advance Echelon, under Colonel Traub, became the Transportation Section of FECZ.
Within FECZ, the Transportation Section was delegated the task of developing the transportation aspects of the plan. Working closely with SHAEF, the 21 Army Group, which was to be the first Allied headquarters on the Continent, and the US First Army, which was to control initial US forces and operations on the far shore, Traub's organization was able to formulate the general outlines of the personnel and equipment requirements and the functions and responsibilities of the Transportation Corps on the Continent. The transportation plan was incorporated into the FECZ plan, which was issued for distribution on 14 May 1944.3
The logistical plan proved a valuable contribution, but FECZ headquarters never operated on the Continent in the manner intended. For reasons that will be discussed later, the date at which it was to take over direction of logistical operations was delayed, and Communications Zone headquarters was phased forward to arrive on the Continent earlier than planned. Transportation Corps personnel of FECZ
who moved to the Continent served with the Advance Section, and were later returned to the chief of transportation upon his move to the Continent with Communications Zone headquarters. The Advance Section (ADSEC), Communications Zone, formally activated at Bristol in February 1944, was to be the first US Army logistical agency on the Continent. Initially attached to the US First Army, ADSEC would gradually take over Communications Zone activities, and, upon the assumption of control of those activities by FECZ and the establishment of additional base sections, move forward behind the armies to provide close continuous support. ADSEC was charged with detailed planning for the period from D Day to D plus 41, at which time FECZ was expected to take over.4The formation of an ADSEC transportation headquarters began in February 1944 when a small group of men from the 4th Port and the 3d Group Regulating Station under Colonel Sibley, former commander of the Mersey area ports, was gathered together at Transportation Corps headquarters at London. Initial activity dealt mainly with plans for the operation of Cherbourg, since Sibley had been designated to take command of that port. Shortly thereafter, Col. William C. Koenig was appointed transportation officer, and served in that capacity until the transfer of the Transportation Section to Bristol in March. There, Col. George W. Beeler was appointed transportation officer, his staff was augmented, and the scope of planning was greatly expanded. By the end of the month, divisions had been established covering all major transportation activities, including movements, and highway, rail, and marine operations. In the remaining period before D Day, additional Transportation Corps personnel were assigned from traffic regulating groups and replacement centers, and on 8 May an Ordnance officer, Col. Clarence W. Richmond, was assigned to the section to organize a motor transport brigade, which was to control all motor transport units on the beaches and at the Normandy ports. During this period, the section prepared several standing operating procedures covering traffic control, motor convoy operation, and other projected activities of the Transportation Section or its divisions.
The principal planning achievement of the ADSEC Transportation Section was its program for the period from D Day to D plus 41, which was issued as part of the ADSEC NEPTUNE plan on 30 April 1944, and finally revised on 1 June. This plan was drawn up in co-ordination with the FECZ Transportation Section, and while it differed in some respects from the FECZ plan it had the effect of filling in the outlines of that plan for the ADSEC period of responsibility. While the plans in general agreed on the role of the Transportation Corps at various phases of OVERLORD, the ADSEC plan was more specific and detailed. For example, the FECZ plan only set forth the type of transportation units required at each stage of operations, while the ADSEC plan included detailed schedules for the timing of the arrival and the initial location of each of the 234 transportation units that were to engage in operations on the far shore during the first forty-one days.5
By D Day there were in existence plans covering virtually every aspect of transportation operations to be undertaken on the Continent during the OVERLORD period. These were part of over-all plans for the development of logistical operations in an evolving communications zone. In general, it was contemplated that US and British forces would control separate lines of communication, with coordination provided by 21 Army Group. In the American zone, the First US Army would control all tactical and administrative activities until the advent of the 1st US Army Group, which would take over upon the arrival of a second American army headquarters. Planning as of D Day
During the first forty days after D Day, according to the plan, the US lines of communication would be extended in a north-south direction along the axis Cherbourg- Vitré. Men and supplies would come in over the beaches and through the ports of the Cotentin peninsula and flow southward to depots or direct to using units. All logistical operations were initially to be under the command of the First Army. Personnel and equipment for beach operations were to be provided by the First Army and its attached Advance Section, Communications Zone. As tactical forces moved forward, ADSEC would gradually take over communications zone activities, including the operation of ports, motor transport, and railways. By about D plus 20, First Army would draw a rear boundary. ADSEC would then be detached from First Army, take control of activities behind the rear boundary, including the beaches and ports, and in effect act as Communications Zone headquarters. Supervision of ADSEC would be exercised by FECZ, first attached to the 21 Army Group staff and later to the 1st Army Group.
It was expected that beginning approximately D plus 41 the lines of communication would gradually shift from a north-south to a west-east direction. With the uncovering of the Brittany ports, the flow of supplies would more and more move eastward along the axis Brest-Le Mans. A base section would be brought in to develop the Brest and Quiberon Bay areas in Brittany. At this point, FECZ headquarters would become operational and assume control of the entire Communications Zone. As the west-east line of communications was developed, ADSEC would move forward to provide direct support to the armies, and a base section would be organized to take over command of the area it had relinquished. The groundwork would then be laid for the transfer of Communications Zone headquarters from the United Kingdom to the Continent on D plus 90.6
General Concepts
The phasing of logistical operations and commands was planned with a keen awareness of their transportation implications. From a transportation point of view, the major problems were expected to be the development of sufficient beach and port capacity and the establishment of adequate motor transport operations. Since Allied planners recognized that prolonged
dependence on beaches and unprotected anchorages might well prove disastrous, they provided for the erection of two artificial ports on the far shore, one to be American-operated, and for the early opening of Cherbourg and a number of minor Normandy ports. Mindful of the World War I experience, the Allied planners relied on the capture of the Brittany ports, notably Brest, to furnish enough capacity to handle a large part of the incoming traffic in the latter stages of the operation. It was contemplated that the lines of communication would have to depend on motor transport for much of the OVERLORD period, with such relief as could be provided by pipelines. Destruction of rail facilities was expected to make rail operations impracticable before D plus 50, other than for local port clearance, and to limit traffic for some time thereafter.7Transportation planning dealt with the phasing in of transportation headquarters, units, and equipment and the progressive development of activities at each stage of operations. During the first phase, D to D plus 25, the Transportation Corps would provide troops and equipment to assist the Engineer special brigades assigned to the First Army in the discharge of cargo, vehicles, and personnel through the St. Laurent-sur-Mer (OMAHA), La Madeleine (UTAH), and Quinéville beaches, the artificial port at St. Laurent-sur-Mer (MULBERRY A), and the nearby minor ports of Isigny, Grandcamp-les-Bains, and St. Vaast-la-Hougue. The Corps would also furnish men and equipment to ADSEC to operate the ports of Cherbourg, Barfleur, and Granville; clear supplies from ports to forward depots and units; establish traffic control in the major port area; operate any rehabilitated railway rolling stock that had been captured; and supplement pipelines and the Army's organic transportation in hauling bulk and packaged POL to the First Army. These activities would be directed by the ADSEC Transportation Section, which also would be preparing to take over transportation responsibilities for the area that was to become the communications zone. By D plus 25, some 24,242 Transportation Corps personnel would be on the Continent, exclusive of those on the beaches.8
From D plus 26 to D plus 41, the ADSEC Transportation Section would in effect be the transportation headquarters for the communications zone, assuming responsibility for the provision of transportation for the support of the US forces. It would operate all major and minor ports, including St. Malo; control marine traffic by recommending ports of entry to SOS headquarters; operate and maintain railways as they were brought into service; conduct motor transport operations necessary for port clearance, static operations, and line of communications hauling, including the movement of POL from ports, beach areas, and pipeline terminals; provide traffic regulation on highways and railroads; and set up regulating stations to control movement across Army rear boundaries. It would also prepare to turn over to Communications
Zone headquarters and base sections such transportation units, installations, and activities as could not be carried forward in the advance. By D plus 41, there would be 36,811 Transportation Corps troops under ADSEC. The bulk of this personnel would consist of port and truck troops, although railway, harbor craft, marine maintenance, amphibian truck (DUKW), traffic regulation, and base depot units also would be on duty.During this period the FECZ Transportation Section would be concerned mainly with the provision of units and equipment to ADSEC, and with preparations to take over communications zone operations. It was also to begin organizing rail operations and to phase in Transportation Corps troops and equipment for attachment to the two base sections that were to be set up behind ADSEC.
In the final phase, D plus 41 to D plus 90, the FECZ Transportation Section would operate as the transportation corps in the communications zone. It would assume control of rail and motor operations, allocate to ADSEC and the base sections personnel and equipment to operate ports, line of communications hauling, and traffic control, and phase in additional units which would be required. It was expected that during this period the Brittany ports of Brest, Quiberon Bay, and Lorient would be opened, rail operations would be organized under FECZ direction by the 2d Military Railway Service, and planned rail and road networks would be placed in operation.
Beach and Port Operations
The development of beach and port operations was planned to provide for a capacity somewhat in excess of that actually required for the support of the forces moved to the Continent.9 Discharge capabilities were expected to expand from approximately 14,700 long tons per day on D plus 10 to about 45,950 long tons by D plus 90.10 The OMAHA, UTAH, and Quinéville beaches were to begin discharge on D Day. The artificial port at OMAHA would be opened on D plus 12, and the small nearby ports of Isigny, St. Laurent-sur-Mer, and St. Vaast-la-Hougue between D plus 12 and D plus 21. These installations would be operated by the Engineer special brigades, with the assistance of Transportation Corps troops, including a major port headquarters, port, amphibian truck, harbor craft, and truck units, and a large supply of floating and materials handling equipment.11Meanwhile, Cherbourg would be opened on D plus 11, and was to be operated by the 4th Port, with attached troops and equipment. Rehabilitation activities of the Engineers were to increase the port's discharge capacity to 5,000 long tons per day by D plus 20, and 8,000 long tons per day by D plus 90. The 4th Port was also scheduled to operate Barfleur and Granville, ports capable of handling coasters only, which would be opened on D plus 20 and 25, respectively. At each of these installations, port troops would be phased
in to keep pace with the discharge capacity of rehabilitated facilities.12In the Brittany area, St. Malo and the nearby beaches were scheduled to begin operation under the 12th Port on D plus 25. With anticipated capacity of 2,000 tons per day by D plus 40 and 3,000 tons daily by D plus 90, this area was to sustain the U.S. Third Army and possibly to handle the debarkation of Third Army troops. The other Brittany ports were expected to come into the logistic picture between D plus 53 and 57, with the opening of Brest and the Rade de Brest, Lorient, and Quiberon Bay.13 The planners estimated that these ports would provide a daily discharge capacity of 8,040 long tons by D plus 60, and 14,550 long tons by D plus 90.
Port planning proved overoptimistic. The capture of Cherbourg was delayed, and its rehabilitation was slower than expected. Moreover, the Brittany ports were not opened as planned because of the late date of the capture, the extent of destruction, and the rapid eastward advance of the armies. In the end, only a few minor ports were operated in the Brittany area. The failure of plans for the Brittany ports to materialize made a heavier and more extended dependence on the beaches necessary, forced a sharp upward revision of Cherbourg's capacity, and posed a port development problem that was not solved until the opening of Antwerp in late November 1944.
Motor Transport
When D Day arrived, the least satisfactory aspect from the standpoint of the theater chief of transportation was the preparation for US motor transportation operations on the Continent. Despite early requests, he had been unable to obtain troops and equipment in quantities sufficient to meet what he considered essential requirements.Immediately upon the reassignment of motor transport operations to the Transportation Corps in July 1943, General Ross had ordered his Motor Transport Division to begin planning for continental operations. Lacking an over-all operational plan, Ross's planners relied on the theater troop basis to work out motor transport requirements for projected port clearance, depot and other static operations, and line of communications hauling. They assumed the use of standard truck companies, each operating forty so-called 21/2-ton vehicles, which actually moved a 5-ton pay load. Estimating the maximum average forward range of a single driver at fifty miles per day, each truck company would have a capacity of 10,000 forward ton-miles per day. On this basis, they calculated that 240 truck companies would be necessary. The G-4 staff believed the number to be excessive, and the theater approved only 160 truck companies. Although the theater troop basis was later increased, and the scope of US tactical operations expanded, no changes were made before D Day in the number of projected units.14 An officer who served
with the SHAEF Movements and Transportation Division has stated that the theater Transportation Corps planners were unable to back up their claims because they lacked basic operational and logistical data such as detailed information regarding the planned deployment of US forces on the Continent, and that the G-4 staff disregarded their recommendations without sufficiently reanalyzing the problem.15Equally frustrating were the Transportation Corps' efforts to secure heavy-duty equipment. A study of the experience in North Africa had clearly revealed the need for trucks capable of handling oversized and bulky supplies and equipment and had demonstrated that the larger vehicles were much more economical in over-the-road hauling than the 21/2 truck. Profiting from this lesson, Ross directed his Motor Transport Division to include in its plans provision for such heavy-duty and special equipment as would be required for a balanced truck fleet. In August 1943 requisitions were sent to Washington for special vehicles with which to re-equip over two thirds of the projected 160 truck companies. Fifty-nine companies were to be provided with 28-foot, 10-ton semitrailers; 36 companies with 21/2 6x6 cab-over-engine trucks, which because of their longer body and greater cubic capacity could carry heavier and more bulky freight than the standard 21/2 truck; 27 companies with 750-gallon tank trucks; 9 companies with 2,000-gallon semitrailer tankers; and 2 companies with 45-ton tank transport trailers and 5-ton refrigerator vans.16
The requisitions fared badly in Washington. Considerable time was consumed in processing papers, and final War Department approval of the projects was not given until December 1943. Several more months transpired before production was initiated so that few of the vehicles had arrived in the United Kingdom by 31 May 1944.17 Pending the receipt of the equipment, the Transportation Corps, shortly before D Day, agreed to accept several alternative types then available for immediate shipment to the theater. Among the substitutions were 11/2-ton truck-tractors with 3-6-ton semitrailers, and 4-5-ton truck-tractors with 16-foot semitrailers that had been designed originally for use in the China-Burma-India theater. Also, some increased carrying capacity became available in May 1944 when the War Department authorized loading up to 100 percent in excess of the rated capacity for 21/2 6x6 trucks operating under favorable conditions on smooth hard-surface roads. The heavy-vehicle project was not to be completed until late in November 1944. In the interim, the Transportation Corps was compelled to rely heavily on 21/2 trucks, supplemented by such other vehicles as could be provided.18
Believing that there would be insufficient carrying capacity even if the heavy equipment should be made available, the Transportation Corps planners sought to
apply another lesson learned during the North African campaign by providing two drivers for each vehicle in order to make possible twenty-four-hour vehicle operation. Their request for overstrength truck units was at first turned down by the theater G-3, on the grounds that such operations would not be required over an extended period of time and that the normal truck company could work continuously over short periods of time if necessary.After repeated efforts by the Transportation Corps to have the matter reconsidered, General Lee became interested in the problem in early 1944 and intervened. Requests for men to provide forty extra drivers per company were then submitted to the War Department. The War Department notified the theater that its troop strength could not be increased, and suggested that the extra personnel be secured within the theater. In April 1944 General Lee directed the base sections to furnish quotas of drivers by a deadline date. Although he specifically stated that he would tolerate no unloading of undesirables, many of the men received proved to be of poor quality. This factor, together with the fact that insufficient time remained for proper training, was later to have an adverse effect upon vehicle maintenance and operation. Additional drivers were secured by distributing personnel from fourteen truck companies among other units, and assigning their equipment to two Engineer general service regiments that were converted into truck companies.19
Meanwhile, FECZ and ADSEC organization and planning had gone forward. Most of the Motor Transport Division staff members at Transportation Corps headquarters had been reassigned to the FECZ Transportation Section, and within ADSEC a Motor Transport Brigade had been organized.20 From D Day to D plus 25, the ADSEC Transportation Section, through its Motor Transport Brigade, would operate the motor transport required to clear ports and to supplement the First Army's organic transportation. Thereafter, until D plus 41, it would be responsible for furnishing general-purpose transport for hauling supplies forward from the beaches, ports, and depots in support of the armies, the Ninth Air Force, and Communications Zone installations. On D plus 41 the FECZ Transportation Section would assume control of motor transport operation in the communication zone and allocate to ADSEC and the two other base sections personnel and units to perform truck hauling and traffic control. There were to be 130 truck companies on the Continent by D plus 41. Transportation Corps theater planners were unhappy about this number, and as D Day approached they were endeavoring to arrange for the earlier employment of some of the thirty truck units scheduled to arrive between D plus 41 and D plus 90.21
The effort to phase in units at an earlier date than originally planned, as well as the last-minute attempts to increase carrying capacity through the assignment of extra drivers and the acceptance of miscellaneous types of heavy vehicles immediately available, reflected a growing anxiety regarding the adequacy of preparations for motor transport operations.
In the spring of 1944 a study by the SHAEF G-4 Movement and Transportation Branch, based on the latest information regarding projected troop deployment and phase lines, indicated that there would not be enough truck units adequately to support the US advance, particularly in the period after D plus 41. After a review by SHAEF logistical planners in April had confirmed these findings, the matter was brought to General Eisenhower's attention. Eisenhower then called in General Lee, and a reanalysis was undertaken by the Communications Zone staff.22 As D Day approached it was evident to the Communications Zone G-4 that there would be a shortage of truck companies if maximum traffic developed, but he believed that the shortage might be relieved through temporary SOS utilization of truck units of the second and third armies to land on the Continent. Moreover, he anticipated that the transportation system as a whole would be adequate, if the heavy vehicles on order materialized in time and rail operations were begun by D plus 60.23In actual operations, the shortage of heavy-duty vehicles and truck companies did not immediately become apparent. Indeed, by late July 1944, only 94 of the planned 130 truck units were in operation under ADSEC, and up to that time they were adequate because tactical progress had been unexpectedly slow and road hauls relatively short.24 With the rapid advance of the armies after the breakthrough at St. Lô, the deficiencies soon became painfully evident.
Rail Transportation
The assumption that motor transport would bear the brunt of overland traffic during the first ninety days was premised on the expectation that extensive destruction of railway equipment, track, and structures would severely limit the immediate use of rail transportation. The theater planners therefore placed the main emphasis on repair and rehabilitation of captured railway track and equipment, and assumed that rail operations would have only limited importance even in the latter phases of OVERLORD.25Planning for continental railway operations had a long history. The Transportation Corps Military Railway Division had begun working on equipment requirements in 1942, and plans for the development of a joint stockpile were made by an American-British committee on which the Transportation Corps and Corps of Engineers were represented along with their British opposites. During the BOLERO period a large quantity of motive power, rolling stock, and other rail equipment was assembled in the United Kingdom for eventual transfer to the Continent. A joint British-American Cross-Channel Ferrying Committee, operating under SHAEF, was responsible for programming the sailings to move the pool of equipment to the Continent.
Detailed Transportation Corps operational planning got underway in early 1944 when Colonel Bingham was appointed head of the Military Railways Division, FECZ Transportation Section.
Bingham was succeeded in April by General Burpee, who had given distinguished service in North Africa and Italy. Burpee commanded the 2d Military Railway Service, which had arrived in the United Kingdom at the end of March, and was scheduled to direct rail operations on the Continent. While railway troops underwent training and made preparations for their move to the Continent, Burpee and his staff continued work on the FECZ plan and maintained close co-ordination with the ADSEC transportation and engineering staffs.26As visualized on D Day, the main functions of military railway troops up to D plus 41 would be to reconnoiter and survey lines to be operated; provide construction-work trains and crews to assist the Engineers in rehabilitating the railways; set up and prepare for operation the equipment ferried over or captured; cooperate with the Engineer and Signal Corps in completing required construction; and start rail operations as soon as conditions would permit. Ferrying operations for rail equipment would begin on D plus 25. Rolling stock and locomotives, at first mainly work equipment, would be landed at Cherbourg, the only port capable of handling them and the starting point for rail operations. It was assumed that no repairable locomotives would be captured within the first 30 days, and that until D plus 41 captured rolling stock capable of being rendered serviceable would not be sufficient to offset losses at sea during the ferrying operation.
Personnel requirements for this period were modest. A small party from MRS headquarters would land on UTAH Beach, join the 382d Engineer General Service Regiment, and proceed to the rail line. Upon the capture of Cherbourg, the party was to make a reconnaissance of rail facilities at that port and follow up with a survey of the line as far south as Valognes. Beginning on D plus 18 the remainder of the 2d MRS headquarters would be phased in to complete detailed surveys and initiate operations, and assigned operating units would be brought in. By D plus 41, the 2d MRS was to have available on the Continent one railway grand division, two railway operating battalions, and two railway shop battalions. Operations would have been pushed as far south as Lison, and preparations would have been started to extend them farther southward.27
In the latter half of the OVERLORD period, rail operations were to be expanded as lines were rehabilitated, additional troops and equipment were made available, and the tactical forces advanced. By D plus 90, the MRS would be operating a rail net bounded by Cherbourg on the north, Auray to the southwest, and Le Mans to the southeast. The net would include the double-track line running south from Cherbourg to Lison, where it was connected by a single-track line with Le Mans. Other lines expected to be in operation extended from Lison southwestward via Granville and Dol-de-Bretagne to Rennes, from Rennes westward to Auray in the Quiberon Bay area, and from Rennes eastward to Le Mans. For the operation and maintenance of these lines, the 2d MRS was to be provided with two railway grand divisions, five railway operating battalions, two railway shop battalions, and considerable rail
equipment. Equipment to be ferried to the Continent by D plus 90 included 354 locomotives, 4,136 20-ton covered cars, 1,862 20-ton open freight cars, 519 50-ton flatcars, 395 cabooses, 152 tank cars, 30 refrigerator cars, 54 40-ton gondolas, and other rolling stock including 6 ambulance trains.28Rail transportation was expected to be the backbone of the transportation system in the post-OVERLORD period. Transportation Corps railway planners believed that by D plus 120 there would be in operation an extensive railway system, consisting mainly of double-track lines, which would be based on Cherbourg and the Brittany ports of Quiberon Bay and Lorient and would extend eastward as far as Dreux and Chartres. The planning staff also drew up plans for subsequent utilization of rail lines up to and beyond the German border.29
Provision was also made for the eventual transfer of rail operations to the French. As set forth by a SHAEF directive in July 1944, the transfer in each liberated area was to take place in three stages: Stage (later called Phase) I called for exclusive military operation of the railways; Stage II was characterized by assistance from the French; and Stage III contemplated French assumption of responsibility for railway maintenance and operation.30
As in the case of the ports and motor transport, the actual development of railway operations did not proceed according to plan. The delay in capturing Cherbourg set back the phasing in of railway troops and equipment. Although destruction of rail facilities proved somewhat less serious than anticipated, operations were at first limited by the shallow lodgment area. At the end of July 1944, US rail activity was confined to the north-south lines between Cherbourg and Lison. Beginning in August the MRS-operated lines had expanded, and American rail personnel were greatly augmented. By D plus 90 (4 September) rail operations had been pushed southward to Rennes and eastward beyond Le Mans.31 The progressive extension of rail lines, however, did not keep pace with the lightning advance of the armies, necessitating prolonged dependence on motor transport. Not until the last quarter of 1944 did the railways catch up and surpass truck transportation in the volume of traffic handled.32
Movement Control and Other Transportation Activities
Control of personnel and supply movements in the communications zone was an important aspect of transportation planning, for without such regulation traffic could become quickly and seriously snarled. Responsibility for this function was to pass successively from the First Army to ADSEC to FECZ. Personnel to carry out the responsibility during the ADSEC and FECZ phases were to be provided by the Transportation Corps. The US First Army was initially to control all traffic. During this period detachments from the 3d Group Regulating
Station would arrive, establish traffic control in the Cherbourg port area, and move out to strategic points along the road network. On D plus 25 the ADSEC Transportation Section would assume responsibility for controlling all traffic behind the First Army's rear boundary. Its Movement Control Branch, through coordination with the services, would issue cargo disposal instructions and allocate tonnages for land movement. Additional traffic regulation groups would be brought in and would provide troops for traffic regulation (RTO) installations. These stations, operating under the ADSEC Transportation Section, would be located at strategic roadheads, railheads, and other vital points along the lines of communication.Beginning on D plus 41, movement control would become a responsibility of FECZ and would be exercised through the medium of base and advance section agencies. Movements by rail or road were to be arranged by base section transportation officers, with the FECZ Transportation Section providing over-all coordination. As an exception to this decentralized traffic control scheme, the planners anticipated that certain through motor routes would be regulated by FECZ headquarters. Control of movements along the lines of communication was to be handled by regulating stations, which by D plus 90 would be manned by men from six traffic regulating groups. As visualized in the FECZ plan, these stations were to be responsible for the orderly movement of supplies and personnel to proper railheads and roadheads, and for the evacuation of casualties, prisoners, and salvage. They were to organize classification and dispatch areas and other traffic control points in order to keep traffic moving and prevent congestion at rail and truck terminals and along the lines of communication.33
Regulating stations were also to be set up immediately behind the Army areas to control movements between the communications zone and the combat zone. Although Field Service Regulations provided that such stations would be directly under the theater commander, it was decided to assign them to ADSEC, which was the Communications Zone agency adjacent to the combat area. The regulating officer was to handle movement requests from tactical forces, set priorities, and regulate the flow of men and materials into and out of the Army areas. As will be seen, two such stations were actually set up, one operating behind the US First Army and the other behind the US Third Army.34
Before closing the discussion of transportation planning it should be noted that two pipeline systems were to be operated on the Continent-one based on Cherbourg and the other on Port-en-Bessin.35 Since the Engineers were responsible for construction, operation, and maintenance of the lines, Transportation Corps planning did not deal with them other than to examine their impact on other transportation operations.
Scant attention was given to the development of inland waterways. No important use of this means of transportation was contemplated during the OVERLORD period.
In order to effect the planned invasion of northwestern France by US forces, it was necessary to move troops, equipment, and supplies from stations and depots in the United Kingdom to proper far shore destinations and to deliver them in the amounts and sequence and at the times desired by tactical commanders.36 This task had to be performed without interfering with the simultaneous movement of British forces. It was a complicated undertaking requiring close collaboration among Allied, British, and American agencies. Machinery had to be set up to control the flow of men and materials and to allocate vessels and landing craft. Areas for the assembly, processing, and embarkation of troops and accompanying matériel had to be apportioned for the movement of cargo necessary to support the invasion, and uniform procedures had to be worked out governing the flow of both US and British forces. Mounting the Invasion
The mounting operation involved the advance loading of the assault forces and a portion of those designated for the subsequent build-up. This was to be followed by a gigantic prescheduled buildup, designed to meet the requirements of the tactical forces, that had to be kept within the limits of the shipping available, the outloading capacity of the United Kingdom ports, the receiving capacity of beaches and ports on the far shore, and the uncertainties that might arise as the result of bad weather, enemy sea action, and changes in the tactical situation. In view of the short sea voyage, the buildup was to be effected by a shuttle service between the southern coast of England and northern France. Support shipping direct from the United States would play a minor role in the early stages of the buildup, but would become increasingly important thereafter and contribute the bulk of the supply requirements on the Continent in the latter phases of the OVERLORD operation.
The theater SOS commander had the responsibility for mounting and supporting the US forces engaged in OVERLORD. Within SOS, the chief of transportation, in coordination with the British, exercised executive control of movements of US troops, vehicles, and supplies, including outloadings from the U.K. ports. Actual direction of US mounting activities, including movement control, port, and other transportation activities, was delegated to the base section commanders. Over-all control of the mounting machinery, both American and British, was made the function of the Allied Buildup Control Organization (BUCO).
Participation in Embarkation Planning
Detailed Transportation Corps planning for the mounting of OVERLORD began in early September 1943 when General Ross established an Operational Branch in his Movements Division.37 One of the branch's first tasks was to participate in the development of joint American-British movement control and embarkation procedures. The British Movements Directorate had been working on plans for the movement and control of an amphibious force to be embarked from the southern coast of England,
and in September the British held the exercise HARLEQUIN to test their effectiveness. In this exercise troops were moved rapidly through pre-established movement control areas, passing successively through a concentration area, an assembly area, and a transit area before embarking. Upon the completion of HARLEQUIN, the Operational Branch joined with representatives of the 21 Army Group and the British Movement Control and, on the basis of experience gained in the exercise, began to formulate uniform procedures governing the movement and embarkation of both US and British forces.In the months that followed, general agreement was reached on movements and embarkation procedures. The southern part of England, roughly south of a line between London and Bristol, was accepted as the mounting area, with US forces concentrating in the southwest and British forces in the southeast. In view of the large number of troops involved and the limited camp facilities available in southern England, it was recognized that it would be impossible to move all of the buildup forces into the mounting area before D Day. Therefore, it was decided to have a prescheduled movement of troops into concentration areas, and thence through marshaling areas to embarkation points, either directly or through embarkation areas.
The concentration areas were to be located fifty to sixty miles from the point of embarkation. While in a concentration area units were to be self-sufficient, were to continue their training, and were to take preliminary steps in preparing equipment and securing supplies for the sea voyage. Next, the units were to be sent southward by road or rail into a marshaling area in the order indicated by priority tables prepared by appropriate army headquarters. There, they were no longer self-sufficient and had to be billeted and fed by a static organization. In the marshaling area the units were placed under a security seal, were briefed on the forthcoming invasion, received final issues of supplies and equipment, and their vehicles final waterproofing. Movement from the marshaling area to the point of embarkation was to be by craft or shiploads as required for the assault and the subsequent buildup
The make-up of an embarkation area was a compromise between British and American points of view. In the American zone of southwest England, the marshaling areas lay comparatively near the coast. In the southeast, the British marshaling areas were located further inland to afford maximum concealment and protection. Therefore, the British desired an intermediate transit area adjacent to the embarkation point so as to control movement. To reach a common method of procedure the embarkation areas were set up to include an embarkation regulating point, which for the British could accommodate both troops and vehicles but for the Americans served simply as a traffic control point.
In practice, the Americans found no great need for the embarkation areas, since the proximity of marshaling areas to embarkation points could have made possible control of embarkation of troops and vehicles merely by parking the units along the roads leading to embarkation points, and then bringing craft or shiploads to the embarkation point with motorcycle escort. Each marshaling area was to be employed for that purpose up to 75 percent of its capacity. The remaining 25 percent was to be kept in reserve to accommodate troops and vehicles that might be unable
to move out because of enemy action, adverse weather, or other circumstances. Troops generally were to stay longest in the concentration area, which in many cases was their home station, rarely more than forty-eight hours in the marshaling area, and usually only a few hours in the embarkation area. Apart from movement priorities, the availability of motor, rail, and, above all, water transport was the key factor in the embarkation cycle.The procedures worked out by the British Movements Director and the US theater chief of transportation were published by the theater on 10 January 1944 in a manual entitled "Preparation for Overseas Movement-Short Sea Voyage" (ETO-POM-SSV). The publication divided the mounting operation into four phases-assault, follow-up, buildup, and normal reinforcement. In all four phases troops would flow through concentration, marshaling, and embarkation areas in the sequence dictated by priority tables set up by the tactical command involved. Among other things, procedures were laid down for stripping units of overhead personnel and excess equipment, for loading unit vehicles with organization equipment, and for preparing necessary embarkation documentation. On 31 March detailed technical instructions covering procedures to be followed by US and British movement control personnel in implementing ETO-POM-SSV were issued.
Amphibious Exercises
The movement control and embarkation procedures, as well as loading and unloading techniques and other aspects of amphibious operations, were tested in several US exercises, in which transportation troops participated. Made as realistic as possible, these training exercises helped disclose matters calling for correction.Assigned to Headquarters, V Corps, the first American large-scale exercise, DUCK 1, was completed early in January 1944. DUCK I involved the movement of American troops and equipment, their embarkation in landing craft, and a subsequent assault with naval and air support on the beach at Slapton Sands near Dartmouth, Devon, where tide, beach, and terrain conditions roughly resembled those on the Normandy coast. In accordance with planned movement tables, the troops and equipment were moved from the marshaling areas to the embarkation points. Despite several deficiencies, notably in documentation and timing, the exercise demonstrated that the normal transportation procedure sufficed.
Other assault exercises were performed before D Day. Among other things, they simulated the conditions likely to be found in unloading supplies over an enemy-held beach and provided training for Transportation Corps port troops in discharging cargo from coasters into landing craft and amphibian vehicles. They also furnished experience in handling skidloaded, or palletized, cargo.38 Continuous study and analysis brought further improvements in procedure. The prevailing point of view was that, if difficulties were to develop, it was better by far that they be detected at this time rather than after the assault had been launched. The major series closed
with two full-dress rehearsals for the invasion, TIGER and FABIUS. The first took on a grim touch when German surface craft attacked unexpectedly, causing a heavy loss of life among the Americans.39Movement Control Organization and Procedures
While the amphibious exercises were being held, planning and organization for the actual mounting operation had gone forward. Skeleton staff tables indicating the planned sequence in which ground, air, and service units would embark from the United Kingdom had been drawn up by the First US Army for the period to D plus 15, and by the 1st US Army Group for the period thereafter. These tables were referred to the Concentration Plan Committee established by the Communications Zone G-4 Planning Branch, on which the theater chief of transportation and the Southern Base Section commander were represented. On the basis of these tables, the committee determined the location of each unit as of D minus 35, the sector through which the unit would move, the concentration area camp to which it would be assigned, and the projected date of its arrival at that camp.40The concentration plan assumed a prescheduled movement of troops and vehicles from their home stations to concentration area camps, and then through marshaling areas to points of embarkation, but it was evident from the first that tactical developments and other considerations would in all probability cause the actual flow of units to differ from that set up in advance. In order to provide centralized and flexible control of the buildup on the Continent on a day-to-day basis, the Buildup Control Organization (BUCO) was established in the spring of 1944 under the joint direction of the Allied Army, Navy, and Air commanders in chief. This Allied agency was composed of a US zone staff and a British zone staff, under the chairmanship of a representative of 21 Army Group. The US zone staff was made up of representatives of the American tactical commands and FECZ. BUCO's principal functions were to control the buildup of personnel and vehicles and to set priorities for their movement as desired by the tactical commands and in line with available shipping and craft.41
Under the control of BUCO were two subordinate agencies, Movement Control (MOVCO) and Turnaround Control (TURCO). MOVCO had general control over the movement of troop units from their home stations to embarkation points, issuing instructions for movement to transportation agencies concerned. TURCO, a traffic control agency staffed by American and British naval personnel, was formed to assist naval commanders in the control of the cross-Channel movement of ships and craft, with a view to minimizing the turnaround time.
Although BUCO itself remained in the United Kingdom, shortly after D Day an organization called Little BUCO was set up on the far shore and in effect functioned as BUCO's advance echelon. This agency was attached to the First Army and was staffed by Army, Army Air Forces, and Communications Zone representatives.
It screened and consolidated requests for changes in priorities of troop units and passed them on to BUCO for implementation.The procedures developed by BUCO were designed to provide movement control machinery that could be adapted to the needs of the tactical commanders and the transportation available. At daily meetings BUCO made alterations in priorities desired by the tactical commanders and modified the planned allocation of shipping and craft to meet current requirements. Any alterations of lift as between the Americans and British were arranged by BUCO with 21 Army Group, which was responsible for the allocation of shipping. BUCO broke down the modified priority lists into lists for the several embarkation sectors, showing the sequence in which units would embark in each. The lists were set up three weeks ahead of movement, and on the basis of this information MOVCO issued a force loading forecast for each embarkation sector, covering anticipated movements during the next ten days. These data were subject to change, but provided the base sections and sectors with a basis for planning and preparations.
More important were the force movement tables prepared by MOVCO. Distributed daily to base section headquarters, marshaling areas, and sectors, these tables covered a twenty-four hours' flow into marshaling areas. Showing the allocation of units to ports, the dates on which units would move to marshaling areas, and the priority of loading, the force movement tables served as instructions to transportation agencies to move units into marshaling camps, and provided the basis for breaking down units into ship and craft loads. Within this framework, US movement control functions were performed by Transportation Corps personnel at the theater and base section levels. The chief of transportation exercised technical supervision over American movements and, through his Operational Branch, issued instructions for the movement of units and vehicles to concentration area camps. The flow of troops and vehicles forward from the concentration area was controlled by the base sections, through the medium of the regional movement control organization, which had been set up in the BOLERO period.42
Encompassing virtually the entire mounting area, the Southern Base Section was responsible for the great bulk of the marshaling and embarkation, although the Western Base Section assisted in mounting two airborne divisions and a portion of the seaborne buildup forces. Southern Base Section's four districts, bearing the Roman numerals XVI, XVII, XVIII, and XIX, were the principal administrative units in the mounting process. The latter two districts, on the southern coast of England, corresponded to the staging zones. The zones, in turn, were divided into nine marshaling areas, lettered alphabetically from east to west. Marshaling areas were commanded by officers responsible to the district commanders. The Center Zone, or XVIII District, contained four marshaling areas. Area A, containing the marshaling camps and embarkation points clustered about Portsmouth and Gosport, was to be entirely British; Areas B and C, in the vicinity of Southampton, were to be used jointly by the Americans and British; and Area D, emptying into Portland and Weymouth, was to be completely American.
Southwestern Zone, or XIX District, contained five marshaling areas, all American-operated. These areas, lettered K through O, were to empty through embarkation points in the vicinity of Torquay, Dartmouth, Brixham, Plymouth, and Falmouth.43Embarkation facilities in the Southern Base Section included a large number of artificial loading points as well as piers. Since there were insufficient piers to load all personnel and vehicles on landing craft and vessels, it was decided to construct so-called hards along the south coast of England from Deal westward. Selected and constructed by the British Admiralty, the hards were beaches paved with concrete slabs and connected with the main highways. At these hards, landing craft could lower their ramps and take on men and vehicles. Similar construction was unnecessary in the Western Base Section, which loaded fewer troops and employed coasters and deep-sea vessels.44
Movement through Southern Base Section was effected by Transportation Corps personnel at the various echelons of command. On the basis of MOVCO daily force movement tables, the Regional Transportation Officer, Southern Base Section, issued road and rail instructions for the movement of units from concentration areas into marshaling areas. These instructions were carried out by the district transportation officers and their RTO's. Sector headquarters, agencies set up by the Southern Base Section, controlled movements from the marshaling areas to embarkation points within their assigned territories. Upon receipt of TURCO vessel availability notices and MOVCO force movement tables, the sector broke units down into craft and shiploads, and called them forward from the marshaling areas. In the embarkation areas Transportation Corps personnel received craft and shiploads, and assigned them to temporary parking places pending actual embarkation. The appropriate port commander was responsible for the loading of troops and vehicles at the piers and hards. Actual loadings at the hards were handled by Transportation Corps embarkation staff officers, in conjunction with naval hardmasters.45
To co-ordinate its marshaling and embarkation activities, the Southern Base Section established an elaborate agency known as Embarkation Control (EMBARCO). Its purpose was to maintain current data on units to be moved and the location and capacity of each camp in the U.S. Army concentration and marshaling areas under its jurisdiction. The Western Base Section, which had a far more modest role in the mounting process, had a simpler control mechanism. There the Transportation Corps was made responsible for all movement orders, and, through a sector headquarters at Newport and a subsector headquarters at Swansea, regulated all movements from marshaling areas to embarkation points.46
The Embarkation Machinery Is Set in Motion
Using the embarkation machinery outlined above, the US assault, follow-up, and a portion of the build-up forces were to be loaded before D Day; additional forces were then to be outloaded as required, by a shuttle operation between the south coast of England and the Continent. Assault Force O, consisting of the US 1st Infantry Division and attached troops, was to make the initial attack on OMAHA Beach. This force and its vehicles were scheduled for loading at Portland, Weymouth, and Poole, with the preponderance of vehicles being loaded through Portland. Assault Force U, made up of the 4th Infantry Division and attachments, was to attack UTAH Beach. Personnel and vehicles of the 4th were to embark at Torquay, Salcombe, Dartmouth, and Brixham. A follow-up unit, Force B, built around the 29th Infantry Division, and two airborne divisions (the 82d and 101st) completed the first American contingent in the Normandy invasion. Troops and vehicles of Force B were to embark at Plymouth, Falmouth, and Fowey. The 1st, 4th, and 29th Divisions, which were to be combat loaded, prepared their own loading tables with the assistance of the Transportation Corps. All together, ten transports (APA's and XAPA's) and 539 landing craft were assigned to carry the troops and vehicles for the assault. (Chart 3) The troop and vehicle lift, by sector, was as follows:47
Sector Troops Vehicles
Total 90,562 11,850Falmouth 14,035 2,604Plymouth 22,790 2,595Dartmouth 21,857 3,516Weymouth 31,880 3,135The preloaded buildup forces, consisting of the 2d and 90th Divisions and attached troops, were to embark from the Bristol Channel ports on coasters and deep-sea ships, including a number specially fitted for carrying vehicles. The 2d Infantry Division and attachments, aggregating 23,100 troops and 3,280 vehicles, was to land on OMAHA Beach on D plus 1 and D plus 2. The 90th Division, consisting of 19,340 assault and attached troops and 2,835 vehicles, was to land on UTAH at the same time. Outloading the normal buildup forces that were to follow was to begin on D Day and would be dependent on the utilization of craft and vessels returning from the far shore. The principal obstacles anticipated during this period were the discharge capacity of the beaches, adverse weather conditions, enemy action, and marine casualties.
The embarkation machinery was set in motion in late April 1944, when forces were marshaled to participate in the last amphibious exercises. The loading of the assault and follow-up forces began at the end of May, and was completed on 3 June 1944. The preloaded buildup forces were aboard one day later. Aside from the 5th and 8th Divisions, which embarked from Northern Ireland in late June and early July and the 9th Armored Group which loaded at Swansea in the Bristol Channel area, the bulk of the normal buildup forces moved through the Southern Base Section, with Southampton and its subports playing the major role in outloading.48
Chart 3--Loading of U.S. Assault Forces for Normandy Invasion: June 1944
As men and vehicles began flowing from concentration areas to marshaling camps and embarkation points in the last weeks before D Day, southern England became the scene of intense activity. The traffic in the Southern Base Section was particularly heavy, and in certain cities such as Oxford, Gloucester, and Cheltenham, special movement control points had to be set up with RTO's. The Medical Corps assisted by taking care of casualties en route, and the Ordnance Department supervised the important task of waterproofing vehicles for the amphibious landing and made necessary last-minute repairs.To control traffic in the Southern Base Section, the regional transportation officer, Col. Walter D. McCord, required more than one hundred railway traffic offices for operation under the district transportation offices. Although eleven traffic regulating groups were in operation on D Day, the tremendous movement of troops and supplies necessitated the procurement of an additional fifty officers and enlisted men for duty in the XVIII District, which became the main outlet for all movements following the initial assault. During this period the Transportation Corps was hampered either by an actual shortage of personnel or by the limited value of traffic regulating units, which had arrived so late that proper training and co-ordination proved very difficult. Between 4 June (D minus 2) and 13 June (D plus 7), no fewer than 152,000 troops and 29,000 vehicles were moved into the marshaling areas. During the remainder of the month An average of 15,000 troops and 3,000 vehicles per day entered these areas.49
Meanwhile, the loading of supplies and equipment for the support of the assault and buildup forces had begun. This transportation task was to prove no less difficult than the mounting of troops and vehicles, and required comparable planning.
The OVERLORD Supply Movement Program
The Transportation Corps had begun to plan for cargo movements incident to OVERLORD In September 1943, about the time that it commenced its study of embarkation procedures. In conjunction with the British Office of the Director of Freight Movements, the Transportation Corps Operational Branch undertook a survey of the outloading capacities of U.K. ports and of the ability of the British railways to handle traffic from depots to ports. This study was only exploratory since tonnage requirements of the forces to be engaged in OVERLORD had not yet been determined. By mid-February 1944 G-4 was able to provide the Operational Branch with the tonnage requirements of the Army supply services, and although data on requirements for Air Forces technical supplies and for the US Navy and Civil Affairs were still lacking, the Operational Branch decided to set up a tentative freight movement and shipping program for OVERLORD. In early March berths with an estimated outloading capacity of 27,678 dead-weight tons daily were allocated ,for US and British requirements, with each nation receiving about half the capacity. The American allocation was later increased to 17,903 deadweight tons daily, based on the use of the Bristol Channel ports, Fowey, Plymouth, and part of Southampton. To assist in lifting this American tonnage, the
British Ministry of War Transport made available 184 coasters.50Meanwhile, the First US Army had been assembling supply requirements data for the first twenty days of OVERLORD, and on 15 March 1944 it published its supply plan. The plan outlined daily tonnage requirements for the assault phase, D Day through D plus 2, and the buildup that was to follow. All supplies for the first three days would be preloaded on coasters, LCT's, and LBV's (landing barges, vehicle). Thereafter, shipments would be made by coasters and deep-sea vessels. Tonnage requirements were to rise from 5,326 deadweight tons on D Day to 23,362 deadweight tons on D plus 18. An additional 12,000 tons of supplies, mainly ammunition, packaged petroleum products, and Engineer equipment, would be preloaded on dumb barges. The barges would be towed to Normandy and there driven onto the beaches, where their cargoes could be used as a reserve in the event adverse weather conditions interfered with the discharge of coasters. Later, the First Army published a breakdown of tonnages to be delivered separately to the OMAHA and UTAH Beaches, and projected preloading operations, originally intended to cover only cargo for the assault phase, were expanded to include all supplies required for both the assault and the buildup during the first eight days of the campaign.
At this time the Operational Branch was at work on a plan for the entire OVERLORD period, including the phases after D plus 20 when the 1st Army Group would be responsible for assembling supply requirements. After consultation with the British War Office, the Operational Branch on 26 April 1944 published procedures covering the movements and documentation of supplies from depots through UK ports. These were further elaborated in SOS movement instructions issued on 6 May.
As finally conceived, supply movements were to be divided into four phases. During the first (prestowed) phase, all cargo to land on the far shore from D Day through D plus 8 would be loaded between Y minus 21 (Y Day being the readiness date for the invasion) and Y minus 8. During this period, cargo would be tactically loaded as required by the First Army, using LBV's, LCT's, barges, coasters, and Liberty ships (MTV's) specifically fitted to handle vehicles. The coasters, varying in capacity from 200 to 2,500 tons, were to be the backbone of the fleet. To insure the arrival of the right quantities of required supplies at each beach, vessels would be loaded with mixed cargo. They would be prestowed in accordance with detailed plans worked out by the Transportation Corps' Marine Operations Division in line with tactical requirements. Every effort was to be made to keep the composition of cargo as simple as possible so as to facilitate its discharge and distribution on the far shore.
In the second (sustained movement) phase, supplies would be loaded in the period of Y minus 21 through D plus 11 for delivery on the far shore D plus 9 through D plus 21. In this phase the coasters, including those returning from the far shore, would still be the major carriers, supplemented by MTV's and commodity-loaded Liberties. The coasters, based on specific UK ports, would operate on
shuttle runs between the ports and the Normandy beaches, and cargo would be consigned to UK ports for outloading as shipping became available. Certain commodities, notably ammunition, packaged POL, and heavy Engineer equipment, were to be commodity loaded at designated UK ports. Since it was not known precisely when individual vessels would return and since such ships varied greatly in size and capacity, the preparation of detailed prestowage plans would be impracticable. The port commanders therefore were to be responsible for planning the stowage of vessels as they returned from the far shore.Loading for phase three (maintenance movement) was to take place from D plus 12 through D plus 31 and was to include cargo required on the far shore between D plus 21 and D plus 41. In this period coasters would continue to be important, but ocean-going vessels-Liberties prestowed or commodity loaded in the United States as well as those loaded at British ports-would be used in increasing numbers. It was anticipated that almost all small vessels could be commodity loaded.
During the fourth (change over) phase, loadings would take place on D plus 32 through D plus 80 for delivery to the Continent D plus 42 through D plus 90. In this period, the brunt of the shipping burden would be shouldered by oceangoing vessels, largely from the United States, supplemented by a reduced coaster fleet from the United Kingdom. It was expected that the prestowage of ships in the United States with supplies of known acceptability for immediate discharge on the Continent would eliminate transshipment through the United Kingdom. Also, since reserves would have been built up on the Continent by this time, it would no longer be necessary to outload supplies to fill requirements on a day-to-day basis.51
Although the primary emphasis was placed on the regularly scheduled movement of supplies, it was recognized that the shipment of certain items might have to be expedited to meet urgent needs on the far shore. Therefore, blood, medical supplies, radio sets and parts, and other high-priority freight were to be carried under a Red Ball express system.52 Dispatched through Southampton, express shipments were limited to approximately 100 deadweight tons per day. The first shipment comprised nearly a ton of radio sets and parts destined for OMAHA Beach. Forwarded by truck to the port, Red Ball items as a rule received top stowage so as to facilitate discharge in France. Unfortunately, the desire of the supply services and agencies on the Continent to utilize fully the allotted tonnage capacity occasionally led to the shipment of razor blades, grass seed, and other cargo that could scarcely be considered critical.53
A Greenlight system, limited to approximately 600 deadweight tons per day, was set up to transport ammunition and engineer construction material across the Channel to meet unforeseen tactical requirements. A total of five days was required to move such shipments from the depots to the port by special train and then by coaster to France. To streamline the operation, documentation was simplified. Ships carrying these supplies had a large green disk painted on the bow. The
Greenlight project began on 21 June, and the last shipment left Southampton on 23 July. Most shipments consisted of ammunition and were delivered mainly to OMAHA Beach.54Implementation of the supply movement program involved a multitude of details. Among other things, detailed procedures for traffic control, documentation, packing, and marking were worked out, and specific berths at the various ports on the Bristol Channel and the southern coast of England were selected to handle general cargo, ammunition, or packaged petroleum. Various ports were designated to outload special supplies. Engineer out-of-gauge and heavy equipment, for example, was to move through Cardiff, lumber and piling through Southampton and Barry, and coal through Cardiff and Swansea.
To effect the most economical use of rail transportation and to facilitate outloading, depots were assigned to serve specific port areas, port storage space was provided to accommodate stocks which could be drawn upon during peak operations, and provision was made for the maximum utilization of pier sheds for the reception and loading of cargo arriving from the depots. Cargo would be called forward initially in boatloads in line with prestowage plans. Subsequent shipments, consisting of several days' supply for specific far shore areas, would be consigned to the United Kingdom port commander concerned, who would develop stowage plans to provide for vessels to arrive at the proper beach on the day designated in movements instructions.55
The Operational Movement Instruction, issued jointly by the theater chief of transportation and the British director of freight movements, was the cornerstone of the system governing the flow of supplies and equipment from United Kingdom depots through the ports to the far shore. On the basis of projected daily requirements assembled by the tactical commands, the chiefs of supply services of the Army, Air Forces, and Navy determined from which United Kingdom depots the required supplies and equipment were to be shipped, and indicated to the depots the specific quantities under each priority rating, the destination, and the date of delivery at the far shore.
Upon notice from the appropriate chief of service, the depot or the supply service headquarters involved would prepare the supplies or equipment for shipment and prepare a separate Depot Supplies Shipment Data (DSSD) form covering supplies or equipment for each destination and each date of delivery on the far shore.56 Copies of this form were then forwarded to the Transportation Corps Operational Branch and the local U.S. RTO at the depot. On the basis of the DSSD and the outloading capacity of the ports, the Operational Branch published the Operational Movement Instructions. These instructions included the Supplies Shipping Index number of the shipment-identifying in code the port of loading and the port or beach of destination-a description of the cargo, its dead-weight and measurement tonnage, rail or road paths to be followed, and the time of arrival at the ports. These instructions in effect
served as an order to the depot to ship certain supplies to specified ports on designated dates; to the railway concerned to move such traffic; and to the port to outload such supplies on the date and to the destinations indicated.As the rail cars or vehicles were dispatched from the depot, the local RTO forwarded by teletype a Traffic Dispatch Advice to the port of embarkation. Upon arrival of the shipment, the port commander manifested the cargo to be loaded aboard a particular ship, drew up a cargo stowage plan showing the cargo's location in the vessel, and prepared a "Breakdown of Manifest" for each supply service with cargo aboard. This last form gave a description of the cargo, its tonnage, and hatch location. As the ship was loaded, the port prepared a Graphic Stowage Plan, and indicated the location of any items that would require heavy cargohandling equipment at destination. Once the ships were loaded, their delivery to the far shore TURCO.57
While supply movement plans and procedures were being developed, the Transportation Corps devised several special expedients for delivering essential equipment and material across the Channel. Among these was the use of converted Liberty ships as motor transport vessels to carry trucks and drivers to Normandy. The conversion, which was accomplished by U.S. military railway shop battalion detachments, involved ballasting and flooring off the lower hold, so as to provide space for vehicles in four of the hatches; the installation of deck latrines; and the conversion of the fifth hatch into living quarters for the drivers who accompanied each shipment. The average vessel lifted approximately 120 loaded vehicles and 500 men on each outbound voyage. As indicated earlier, the 14th Port at Southampton took the lead in dispatching MTV's to support the invasion force. At first, vehicles were discharged on the far shore by barge or lighter, using the ship's own gear.58
Under the supervision of the 14th Port, American and Canadian personnel cooperated in building huge rafts, similar to those employed to float lumber on the Columbia River in the Pacific Northwest and consisting of large bundles of wooden poles and piling bound together by cables. They were to be towed across the Channel and landed on the far shore for the use of Engineer and Signal Corps construction units. At Southampton and Poole the 14th Port had the preinvasion project of stowing 104 self-propelled barges (LBV type) with ammunition, petroleum products, and Quartermaster supplies. Because of the supreme importance of having sufficient gasoline and oil was a responsibility of to sustain the Allied air and ground offen sive, the 14th Port was also made responsible for loading a special pool of tankers at the Solent installations of Hamble and Fawley.59
Specially equipped LST's were scheduled to move assembled railway cars to France. Rails were laid on the lower deck, and the ramp was modified. The cars were loaded and unloaded over track laid on improvised shore-side ramps that could be
raised or lowered with the tide. The LST was made fast to the tracked ramp, and the cars were pulled on or off as required. Such ramps were constructed first at Southampton and later in Cherbourg, the principal terminals for cross-Channel railway traffic. By 6 June 1944 some 15 LST's had been converted to ferry rolling stock. Actual ferrying to the Continent was begun in the following month. Larger rolling stock, such as locomotives and tank, refrigerator, and passenger cars were lifted on British sea ferries, on the two American seatrains--the Texas and the Lakehurst--and aboard a number of large car floats that had been towed to the theater from New York. The seatrains operated mainly between Cardiff and Cherbourg, while the ferries shuttled between Southampton and Cherbourg. A Transportation Corps officer, Colonel Bingham, was in charge of the entire ferrying program.60Among its other preparatory activities, the Transportation Corps submitted special procurement projects to augment the supply of floating equipment and to furnish replacements for inadequate cargohandling equipment on British coasters. The Transportation Corps marine equipment, consisting of tugs, barges, small Y-type tankers, and various types of towboats and other craft and manned by both military and civilian personnel, was to prove extremely useful. In the United Kingdom they towed invasion craft to and from assigned berths within the ports. Approximately thirty-four Transportation Corps tugs were assigned to cross-Channel operations. They moved landing craft on and off the beaches, towed units for the artificial harbors, and did sea rescue work. Ten MTL's (motor towboat, large) and at least one tug were lost or damaged beyond repair. Only one of the tankers, the Y-24, was reported a casualty. Beached on the far shore, she pumped gasoline directly into the tanks of waiting trucks. Eventually, most of these vessels were assigned to harbor craft companies and then dispatched to the Continent.61
The signal to begin mounting cargo was given in late April 1944 when Operational Movement Instruction 61 was issued to cover the movement of cargo for preloading on LBV's, LCT's, and dumb barges. Also, separate movement instructions were published for each of the 132 coasters to be loaded at U.K. ports before D Day. A total of 274 vessels and craft were involved in the preload, and stowage plans had been drawn up for each before the issuance of the movement instructions. The preloading of the large fleet of coasters, barges, and landing craft commenced on 4 May 1944. Cargo destined for discharge at OMAHA was loaded between that date and 5 June. During this period 12 dumb barges were loaded at Fowey, 68 LBV's at Southampton and Poole, 7 LCT's at Plymouth, and 80 coasters at Port Talbot, Garston, Swansea, Newport, Barry, Cardiff, and Portishead in the Bristol Channel area. Cargo intended for delivery to UTAH Beach was loaded between 6 and 26 May. In this operation 8 dumb barges, 11 LCT's, and 7 LBV's were loaded at Plymouth, 29 LBV's at Southampton, and 52 coasters at Sharpness, Penarth, Portishead, and
Avonmouth. By D Day a total of 107,606 dead-weight tons had been preloaded for shipment to the far shore. This figure may be broken down as follows:62
Type of Cargo For OMAHA Beach* For UTAH Beach*
POL 18,244 8,070Ammunition 28,754 18,320General Cargo 19,653 14,565
* Dead-Weight Tons On the eve of the invasion the U.S. assault, follow-up, and initial forces, and the supplies and equipment necessary for their support had been loaded and were awaiting call forward. The larger and in many respects the more difficult job of sustaining the build-up on the Continent was still to be performed. United Kingdom outloadings of U.S. troops, supplies, and equipment attained greatest proportions during the OVERLORD period, but continued important through V-E Day.
On D Day the preloading program had been completed, and the sustained buildup phase had begun. Detailed plans had been formulated for a smooth predetermined flow of men, vehicles, and cargo to U.K. ports, and for a continuous shuttle service to transport them to continental destinations. Subject to uncertainties regarding the return of vessels and craft from the far shore, the tactical situation, and the weather, the build-up program ran into difficulties almost from the beginning. Outloading From the United Kingdom
Troops and Vehicles
The build-up of troops and vehicles was handled through Southampton and Portland-Weymouth, although Falmouth and Plymouth were also used somewhat in the early stages. The marshaling of units in the areas that backed up these ports began before D Day. When the invasion was postponed from the 5th to the 6th of June, the British temporarily halted their troop flow, but the Americans continued to move units from concentration areas to marshaling camps and embarkation points.63 This led to the first signs of congestion in the marshaling camps and at the ports. U.S. activities at Southampton, the principal port of embarkation, were almost nil on D Day, since the British were using the area to embark their forces, but beginning 7 June the port was crowded with marching columns of U.S. troops and long convoys of vehicles, tanks, and other matériel. At the outset the port experienced a serious shortage of personnel, and there were not enough vessels and craft to lift all the forces moving into the port area.The week that followed was attended by congestion, confusion, and a temporary loss of control of the mounting machinery. There were several factors responsible for this state of affairs. In the first few days, movements forward from concentration areas conformed to the U.S. First Army's build-up priority tables, but thereafter the tactical situation dictated frequent
changes in priorities. These changes were incorporated into MOVCO's force movement tables, which were implemented by Southern Base Section. Soon there was little relation between the planned sequence of movements and the actual flow into marshaling and embarkation areas. The frequent changes in priority caused heavy congestion in the marshaling camps, for once a unit had been moved forward, it had to be held in the camp while higher-priority units were processed and sent through ahead of it. Moreover, priorities were often set by the tactical command on the far shore without regard to the readiness of units. This resulted in many being called forward before they were properly equipped and organized. Other units, desiring to keep their troops and organizational equipment intact, did not shed their overhead personnel and excess equipment in the concentration area as provided for in the embarkation procedure, but took them along to the marshaling camps, thereby contributing to the congestion. Finally, ships and craft did not return from the far shore in the number or at the time expected, so that more troops were in embarkation areas than could be loaded promptly.64The magnitude of the operation, frequent changes in priorities, the lack of shipping, and other difficulties caused a disorganization of the mounting machinery that attained serious proportions between 9 and 12 June.65 Marshaling areas were clogged, ports were crowded, and advance information regarding the availability of craft was lacking. EMBARGO could not keep up with the frequent changes in the status of troops, and in many cases was unable to furnish accurate information regarding the location of units. At Southampton loading tables issued by sector headquarters before the arrival of units proved erroneous, so that all planning and loading had to be effected after the units had arrived, when the actual number of troops and vehicles could be determined.
In an effort to dissipate the tie-up, on 9 June BUCO ordered the loading of units on vessels as rapidly as possible regardless of priority and directed the temporary curtailment of movements into the marshaling camps behind Southampton. Units were then moved into embarkation points and loaded on ships and craft as rapidly as they became available. At the piers and hards, embarkation had to be accomplished on short notice and often without the benefit even of hurriedly prepared plans. In some cases no records were kept of these loadings, a deficiency that might have proved serious had shipping losses occurred.
Through strenuous efforts, which left not a few officers and enlisted men on the point of exhaustion, the situation on the near shore was improved. There is little evidence that either administrative confusion or congestion of the marshaling areas persisted after 12 June. Outloadings continued to lag, however, because of the limited reception capacity on the far shore, the slow turnaround of vessels, and the shipping shortage. The decline in
outloadings was halted and reversed on 18 June, but the onset of the violent storm of 19-22 June reduced cross-Channel movements to a trickle. Thereafter, the buildup proceeded in a far more orderly fashion.66 Toward the end of the month the theater requested and received additional LST's and MTV's. By July the control of movements was effective, and vessel availability had greatly improved. Although difficulties continued to arise, the principal bottlenecks had been broken.From the experience in the United Kingdom, particularly during the first weeks of the build-up, certain conclusions may be drawn regarding some of the major causes of the difficulties encountered. One deficiency that appears evident in retrospect is that BUCO lacked sufficient authority to regulate the mounting machinery in a fully effective manner. Although charged with responsibility for controlling the build-up, BUCO was not formally an agency of SHAEF, 21 Army Group, or the First U.S. Army. To carry out its mission BUCO had to deal with the many agencies involved in the embarkation process, and its uncertain authority made the co-ordination of activities extremely difficult, and sometimes delayed corrective action. A theater General Board study made after the war concluded that a central organization should have been set up, responsible directly to the highest tactical commander involved in the operation, and authorized to represent him on all matters affecting the build-up.
A Transportation Corps movements official suggested that wasteful duplication in higher headquarters could have been eliminated if all build-up planning had been centralized in BUCO. Under this concept representatives from the Southern Base Section and its districts and from theater general staff sections should have been placed at BUCO to plan and change priorities and indicate the concentration area or marshaling area to which they desired units moved. These instructions could have been given to the Operational Branch, which through Transportation Corps channels would have controlled actual movement from home station to concentration and marshaling areas.67
As has been stated, the frequent changes in the priority of units posed serious problems. Such changes tended to congest marshaling areas, hindered normal troop movements, created confusion, and sometimes resulted in split shipments. Occasionally, units were phased forward as much as three weeks, and in several instances units were called up before they had been fully equipped. However, the difficulties were to a large extent unavoidable, since most changes were dictated by the tactical situation. Less justifiable was the failure of many unit commanders to adhere to established mounting procedure. This applied particularly to the provision for stripping units in the concentration areas of overhead personnel and of organizational equipment other than that carried in unit vehicles. According to the plan, the equipment would then be shipped as freight so as to arrive on the far shore shortly before
the unit. The residual personnel would follow later. During the actual mounting process, however, many unit commanders took all their vehicles, troops, and equipment into the marshaling camps, insisted that they be loaded, and resisted the splitting up of their unit into craft loads for embarkation. This aggravated the congestion in marshaling camps, and tended to disorganize movement and loading activities. Since the constant shifting of priorities for units upset the scheduling of shipments of organizational equipment and occasionally caused delays in delivery or losses, the attitude of unit commanders is understandable. Nevertheless, there is little doubt that had the commanders conformed to the procedure set down in the POM-ETO-SSV, the flow of troops and equipment would have been greatly expedited. The problem of placing organizational equipment on the far shore when needed could have been handled by giving such equipment priority treatment.68Another deficiency involved the manning of camps and other installations engaged in the mounting operation. Still heavily engaged in the BOLERO program, the SOS organization had been unable to provide sufficient personnel in advance to receive training in mounting procedures. Also, it proved necessary to use units intended for eventual movement to the Continent for housekeeping functions, and when these units were moved out they were replaced by troops not trained for their work. Inexperience and lack of training inevitably had an adverse effect on the processing of units and slowed the mounting process.69
Outloadings of personnel and vehicles reached a peak in July 1944 and continued heavy through September. During this period there was some simplification of organization and procedures in the Southern Base Section. Beginning in July, troops scheduled for loading on deep-sea troop transports were entrained at concentration area camps and moved directly to the water front. In the following month, Marshaling Area "C," which funneled units into Southampton, was turned over to the 14th Port. Previously, this marshaling area had been run by the Sector Headquarters, which had controlled the movement of units to the embarkation points. With this transfer, the area became the staging area of the 14th Port, which was given responsibility for the movement of troops from there to loading points.70
By the end of September 1944, a total of 1,462,426 personnel had been outloaded from the United Kingdom for the Continent. The heaviest embarkations of men and vehicles were over the piers and hards at Southampton. In the period 6 June-6 September 1944, 686,868 personnel were embarked at this port on LSI's, MTV's, LST's, LCI's, and LCT's, and 140,303 vehicles were loaded aboard MTV's, LST's, and LCT's. Southampton also handled patients and prisoners of war evacuated from the Continent. In addition, the port played an important role in the outloading of cargo, rolling stock, and bulk POL.71 The port facilities were shared by the Americans and the British on a day-to-day allocation made in accordance with the tactical needs.
Portland-Weymouth ranked second as an embarkation area, handling a daily loading program of 10,500 troops and 1,500 vehicles aboard LSI's, LST's, LCI's, and LCT's. Plymouth and Falmouth were active as MTV loading ports until the latter part of July, moving a total of 60,152 troops and 17,386 vehicles. The Bristol Channel ports were primarily used for loading cargo and played only a small part in personnel and vehicle embarkations. After preloading 42,410 troops and 6,435 vehicles, these ports outloaded less than 6,200 personnel and accompanying equipment during the next three months.72In September, when the great bulk of troops scheduled for the movement from the United Kingdom to the Continent had been outloaded, BUCO and EMBARCO ceased to function. Their responsibilities were turned over to the United Kingdom Base Section, and the U.S. MOVCO staff was absorbed by the office of the theater chief of transportation. Thereafter, priorities were set by the United Kingdom Base Section G-4, with the Transportation Corps Operational Branch (later Movements Division) controlling the movement of all units through all stages into the marshaling (staging) area. Movement control was effected in co-ordination with base section (later district) transportation officers, and United Kingdom port commanders.73
It had been expected that troops would move from the United States directly to the Continent after September, but inadequate port and staging facilities on the far shore led to a continuation of important outloading activities from the United Kingdom. From September 1944 through VE Day, large troopships, including the Queens, the Mauretania, and the Aquitania, brought U.S. troops into the Clyde and Mersey ports for immediate transshipment to the Continent. These troops were then moved by train to Southampton and its subports in the Portland-Weymouth area, which at that time was handling all cross-Channel troop shipments. Despite some interference with the normal movements of units to the Continent, a shortage of shipping, and bad weather, the transshipment program was accomplished smoothly. With the exception of periods of adverse weather conditions, troops were disembarked at the Clyde and Mersey areas and re-embarked at Southampton and Portland within eighteen hours. The transshipment operation ultimately involved eighty-two troop transports, over 300,000 troops, and the operation in Great Britain of 742 special trains.
The U.K. base also was called upon, beginning on 1 October, to handle convoys carrying troops and their organizational equipment and supplies from the United States that were intended originally for discharge in France. These troops were staged and processed in the United Kingdom, and later moved to the Continent. The Transportation Corps Operational Branch was responsible for moving the troops and their equipment from ports of debarkation to designated locations in the United Kingdom. The convoys, which continued to arrive through 6 January 1945, totaled 83 troopships and 91 cargo vessels, carrying 269,822 troops, 547,608 measurement tons of organizational equipment, and 330,027 measurement tons of general cargo. Most
of the cargo vessels were discharged at the Bristol Channel ports, while troopships were unloaded at ports on the southern coast and in the Bristol Channel, Clyde, and Mersey areas. Also, forty-five vessels carrying boxed vehicles intended for troops who had arrived in the convoys were discharged at U.K. ports.74As the result of the continued movement of men and vehicles into the United Kingdom, outloadings to the Continent remained important into the spring of 1945. By V-E Day, a grand total of 2,480,432 U.S. troops and 422,608 vehicles had been loaded out from the United Kingdom for delivery to the Continent.75 These figures represent but part of the activity of the U.K. ports, for at the same time they had been handling the large volume of supplies and equipment required to support the build-up of U.S. forces on the far shore.
Cargo
As in the case of troop embarkations and vehicle loadings, the supplies and equipment for the assault and initial buildup phases of OVERLORD had been preloaded. On D Day cargo destined for delivery to the Normandy beaches during the first eight days of the invasion had been placed aboard coasters, barges, and landing craft. Although some additional vessels were immediately available for loading supplies for delivery after D plus 8, the sustained build-up phase of the supply movement program was dependent on the return from the far shore of the coasters that were to operate on continuous shuttle runs from southern coast and Bristol Channel ports.Despite light losses at sea, the anticipated prompt turnaround of vessels did not materialize. At the Bristol Channel ports, for example, coasters did not begin to arrive from the far shore until the second and third weeks following D Day. Meanwhile, the chief of transportation had ordered supplies and equipment from depots to U.K. ports to meet the projected daily requirements of the tactical forces on the Continent. As a consequence, the ports were soon glutted with cargo far in excess of available shipping, and deliveries to the far shore lagged behind the requirements of the tactical forces.
The underlying cause of the tie-up at the ports was the failure of vessels to return promptly for reloading, and this was the result of delays in landing cargo on the far shore. As will be seen, selective discharge, adverse weather conditions, delayed delivery of manifests, and dependence on lighterage and improvised cargohandling methods all contributed to this lag. As the result of prolonged beach operations and delays in opening and developing ports on the Continent, ship turnaround continued to be a problem well into the fall of 1944, and the coaster fleet failed to live up to its planned capabilities.76
As early as 10 June 1944 it became apparent that the coaster fleet would not deliver the tonnage required on the far shore. Although the Operational Branch argued that loading additional vessels would not necessarily increase the
discharge over the beaches, it received orders to increase outloadings. The Operational Branch accordingly arranged for the loading of 100,000 measurement tons of cargo on ten Liberties by the end of June.77Meanwhile, the U.S. First Army had steadily increased its supply requirements. Since not enough shipping was available to lift such tonnages, the problem of priorities arose. Each service understandably pressed to accelerate the movement of its own supplies from the United Kingdom. The constant interjection of priority shipments had a disturbing effect on the flow of traffic from depots to ports. Depots often had to suspend work in the middle of a shipment to work on priority cargo, and therefore the port found itself with an incomplete shipment on hand and had to wait several days for the remainder. Priority shipments upset packing and marking at the depots; tended to cause congestion at the ports; and necessitated the cancellation of previously scheduled trains, thereby causing congestion at the depots and tying up rolling stock for extended periods.
Although Transportation Corps movement officials realized that priorities were inevitable in view of the tactical situation, they believed that requests should have been more carefully screened and that they should have been limited to justifiable cases. In their opinion the priorities granted were often unnecessary, a contention that was given weight since some ships carrying priority cargo in the latter part of 1944 were allowed to lay at anchor off the far shore for weeks at a time.78
The necessity for meeting far shore requirements on a daily basis hampered the efficient movement of supplies from United Kingdom depots. As already indicated, tonnage requirements were prede termined by the First Army and 1st Army Group according to the date of discharge on the Continent. The idea behind this procedure was that a certain amount of each type of supply, including ammunition and packaged POL, should be discharged daily. A portion would be immediately used, and the remainder would be held to build up a reserve. Requisitions processed by the tactical commands were prepared for each day of discharge. Each item of supply was broken down into daily shipments, and vessels were to be loaded so that cargo scheduled for discharge on a designated date would be available at the proper time.
Implementation of this procedure involved a tremendous amount of planning by Transportation Corps movements control personnel and complicated the work of the U.K. depots and ports. The movement of supplies for delivery on a day-to-day basis made it necessary for depots to prepare a large number of small packages for shipment. The packages had to be scheduled for movement by rail or highway in such a manner as to arrive at the port when required. At the ports, coasters had to be loaded in such fashion that a certain tonnage would be available for discharge on a given day. For example, a coaster that required three days to unload, would be bottom-stowed with cargo for discharge on the third day. The second day's cargo would be placed above that, and the first day's cargo would be topstowed. Since coasters varied greatly in size and construction, stowage for each had to be carefully planned in order to meet these daily requirements. Aside from the elaborate paper work and documentation
involved, this procedure placed a heavy burden on port storage facilities since the port could not load cargo for delivery on the first and second day until the third day's cargo had arrived and been stowed. The task was further complicated by continuous changes in supply requirements and by delays in processing requisitions. In some instances, shipping bids (DSSD's) actually arrived at the Operational Branch after the date set for discharge on the Continent. Adjustments naturally proved difficult in view of the fact that the supply plan was based on the maximum capacity of depots and ports and the meticulous scheduling of rail and highway transport.79The scheduling of shipments for delivery to the Continent on a daily basis was continued longer than was necessary. A theater General Board study concluded that while the setting up of daily supply requirements was essential in the initial operations, it was not desirable once some reserve stocks had been accumulated on the Continent. The board found that continuation of this procedure had complicated depot operations, movement to the ports, and port activities. Its wastefulness becomes even more apparent when it is realized that the vessels on the far shore were not discharged in the planned sequence, but according to needs arising out of the immediate tactical situation. Actual requirements could have been met more readily if the daily requisitions had been eliminated earlier.80
Despite a continuing lag of shipping, the U.K. ports had shipped out a huge volume of cargo by the end of September 1944. Including the preloaded cargo, a total of 1,439,227 long tons of ammunition, packaged POL, and general cargo had been outloaded. Peak loadings came in July 1944, when almost 450,000 long tons were moved out. Although it had been planned to reduce the coaster fleet in the latter phases of OVERLORD, the coaster continued to be the backbone of the supply movement program, being assisted by relatively few deep-sea vessels. Aside from the tonnages listed above, large amounts of railway equipment, bulk coal, and bulk POL were moved to the Continent.81
The Bristol Channel ports of Avonmouth, Barry, Cardiff, Newport, Penarth, Portishead, Port Talbot, Sharpness, and Swansea were all important in the shipment of OVERLORD cargo. Operations were supervised by the 17th Port, under the command of Col. Edward H. Connor, Jr. In addition to loading regular operational tonnage, such as general cargo, packaged POL, and ammunition, a number of these ports handled specialized cargo. Cardiff loaded Engineer heavy equipment and locomotives, principally on Liberties and seatrains. Bulk POL was loaded on tankers at Swansea. From Barry timber was shipped on coasters and Liberties or rafted to the far shore. Bagged coal was loaded at Cardiff and Swansea. Between May 1944, when preloading began, and the end of September, the Bristol Channel ports loaded a total of 868 vessels with 1,037,332 long tons of U.S. cargo. This task was accomplished in addition to routine discharges and loadings, which fluctuated between 104,000 and 246,000 long tons per month.82
On the southern coast, the 14th Port at Southampton, in addition to handling the greatest part of the troop and vehicle embarkation program, outloaded a large proportion of the supplies and equipment moved to the Continent. The 14th Port handled the loading of coasters at Southampton and its subport at Poole; loaded approximately 90 percent of the rail equipment being shipped to the Continent aboard LST's, seatrains, and ferries; and maintained a detachment at Hamble and Fawley to assist in the joint loading of British and American tankers. During the first ninety days of the invasion 14th Port outloadings, including ammunition, packaged POL, general cargo, bulk POL, and vehicles, totaled 990,341 long tons. In the course of loading troops, vehicles, and cargo during this period, the port handled no fewer than 3,517 vessels and landing craft. Other important south coast ports were Fowey and Plymouth, which were used under the supervision of the 13th Port to load ammunition and packaged POL, respectively.83Continental discharge of cargo arriving directly from the United States attained significant proportions in July 1944, and beginning in October increasingly outstripped the tonnage being shipped from the United Kingdom. Outloadings from U.K. ports fell off appreciably in the fall of 1944, but again increased early the next year, reaching near peak proportions in the period March-May 1945.84
Despite a substantial cut in the tonnage allocated for movement from the United Kingdom to the Continent in September 1944, erratic turnaround of coasters and the limited availability of supplementary deep-sea shipping caused the U.K. ports to experience continued difficulty in meet ing outloading targets. By this time, however, movements and loadings in the United Kingdom had become a less important consideration than the discharge and clearance of cargo at continental ports. To facilitate the latter activities, the theater chief of transportation and the Communications Zone G-4 agreed on the adoption of a commodity-loading program. On 26 October the theater assigned ten Liberty ships to shuttle cargo from the U.K. ports to the Continent. As far as practicable, each of the vessels was to carry one class of supply for a single supply service. It further directed that coasters should be commodity loaded whenever possible, and that as a general rule all Quartermaster Class I and II, Ordnance Class II, and Engineer Class I and IV supplies should be so loaded. The supply services and the Air Forces were to project shipping bids for a minimum of one month ahead and to indicate the relative priority of the supplies they desired shipped. All coasters were to anchor off Le Havre and be diverted to Le Havre or Rouen as the situation warranted. The commodity-loading program got under way in November 1944.
At the outset, the U.K. ports encountered some trouble, since it was necessary to segregate their rather sizable cargo backlogs to conform to the new loading schedules. Also, the services failed to maintain the prescribed month's backlog of shipping bids, so that it was difficult to select and organize complete trainloads at the depots and ship supplies in the order of their priority.
In early 1945 it was decided to cut the turnaround time of the coasters by assigning the entire coaster fleet to the south coast ports and to use the Bristol Channel ports to load most of the deep-sea vessels, chiefly of the Liberty and Hog Island types. The coaster fleet then operated mainly between Southampton, Poole, and Plymouth and Rouen. The larger vessels, except for a few used to load packaged POL from Plymouth, operated principally between the Bristol Channel ports and Ghent. The bulk of the cargo on both the coasters and the larger vessels was either commodity loaded or block stowed. This reassignment of shipping paid off in increased outloadings, and in March and April of 1945 the tonnage was surpassed only by the peak month of July 1944.85Shipments of U.S. cargo from the United Kingdom to the Continent continued until several months after V-E Day. The tonnage total is impressive. Including preloaded cargo, a total of 3,065,682 long tons of general cargo, ammunition, and packaged POL was moved from U.K. depots to U.K. ports and thence to the Continent by 8 May 1945. This tonnage was transported principally by a fleet of small coasters, which were supplemented by Liberties and other deep-sea vessels. It does not include approximately 1,151,000 tons of bulk coal and rolling stock, and a large volume of bulk POL outloaded from the United Kingdom. When the 422,608 vehicles and 2,480,432 troops moved from Britain to the Continent are added, the full magnitude of the outloading operation may be realized.86
With the assaults on the OMAHA and UTAH Beaches on 6 June 1944, Engineer special brigade troops, assisted by assigned or attached service units, began the task of beach development and operation.87 German resistance was stronger at OMAHA than at UTAH, but on both beaches enemy shelling and sniping caused delay, damage to equipment, and casualties among the service troops. Cargo discharge was hindered initially by the many beach obstacles set up by the enemy and the inevitable debris and wreckage of the assault period. Mines had to be cleared to permit safe passage across the beaches, and roads had to be constructed. Beach and Early Port Operations
Transportation units participated in beach operations almost from the beginning. Port troops discharged cargo from vessels anchored offshore into amphibian trucks (DUKW's) and Navy ferry craft; amphibian truck units transported cargo from shipside to transfer points or dumps; and truck companies cleared the beaches. The Transportation Corps also furnished a major port headquarters, which had an important role.
OMAHA Beach
The magnitude of the attack by the U.S. V Corps at OMAHA caused the First U.S. Army to provide the support of two Engineer special brigades (the 5th and 6th) and one port headquarters (the 11th). Overall control was vested in a single headquarters, which, with various attached units, constituted the Provisional Engineer Special Brigade Group, under the command of Brig. Gen. William M. Hoge.88 Included in the headquarters was a Port, or G-5, Section, headed by Lt. Col. Carl Biehl, formerly with the 11th Port.While being readied for their mission, the brigades were heavily reinforced with transportation troops. Each brigade was provided with two port battalion headquarters and ten port companies, one amphibian truck battalion headquarters and three amphibian truck companies, and one Quartermaster truck company with 104 vehicles. These transportation units aggregated approximately 6,300 troops, almost one third the total strength of the two brigades. Among other units assigned to the brigades were Quartermaster service companies, which were to handle unloading activities on the beaches, and railhead companies.
The 11th Port was furnished three port battalion headquarters and eighteen port companies, one Quartermaster trucking battalion headquarters and three companies, two amphibian truck battalion headquarters and six companies, one harbor craft company, three Quartermaster service battalions, and other service units, giving it a total strength of about 8,600 officers and enlisted men. In command was Colonel Whitcomb, an experienced officer who had previously served at ports in Iceland and the United Kingdom.89
Transportation Corps units serving with the brigades were scheduled to begin operations on D Day or shortly thereafter. In the United Kingdom, the brigade port companies were placed aboard cargo vessels, which were scheduled to arrive during the first three days of the invasion. After unloading their own vessels, the port troops were to go ashore and there discharge other vessels and craft anchored offshore and under the control of the brigades. Brigade DUKW units, their vehicles preloaded with ammunition, construction materials, and other cargo immediately needed, were to be launched from LST's beginning on D Day. After delivering their cargoes onto the beach, the DUKW's were to shuttle between the ships at anchor and the initial dumps. All DUKW's were scheduled to be in operation by the end of D plus 2. Brigade trucks were to be brought ashore during the first day of operations.90
The 11th Port was not to engage in initial operations. Although an advance party was to arrive fairly early, its port troops were not to begin coming in until D plus 10 (17 June), when the artificial harbor (MULBERRY A) would be about ready for operation. The principal mission of the 11th Port was to be the conduct of pierhead operations at MULBERRY A and at the small ports of Grandcamp-les-Bains and Isigny, which were to be opened at about the same time, but its port troops were also to discharge ships anchored
off-shore, and along with brigade troops operate cranes on the beaches.91The brigade DUKW units began their operations on schedule, first delivering their preloaded priority cargoes ashore, and then carrying cargo from ship to shore and evacuating casualties. Operational difficulties were encountered early. Many DUKW's were sunk or damaged during the landings when they struck enemy-laid mines or other obstacles. Some overloaded DUKW's were swamped, and others, launched too far offshore, ran out of fuel and were lost at sea. Adequate maintenance and repair proved almost impossible because of the shortage of spare parts and the round-the-clock activity.92
The story of the 453d Amphibian Truck Company is illustrative. The unit was alerted on 28 May 1944, and all vehicles with their drivers and assistant drivers were loaded aboard LST's. All other personnel embarked on the APA 77 (USS Thurston). The convoy sailed from Weymouth on 5 June and laid off Normandy until debarkation time on 6 June, when the bows of the LST's were opened some ten to fourteen miles from the coast. The DUKW's rolled off stern first, formed columns, and headed for shore. The one officer and seventy-five enlisted men on APA 77 landed at approximately 1330 of D Day from an LCI, which was hit several times by enemy fire during the debarkation. In the initial operation six enlisted men were killed and seventeen DUKW's were lost. The vehicles could be put ashore only at low tide, when passage was possible through wrecked landing craft and beach obstacles to Road Exit 1.
By